6840 S. Tucson Blvd, Tucson, AZ 85756, U.S.A.
GET A CONSULTATION

CASE STUDY

Port of Long Beach Steel Pipe Pile Repair Without Welding

Two mooring dolphins serving Carnival Cruise Line at the Port of Long Beach had severely corroded steel pipe piles and concrete caps. This steel pipe pile repair used PileMedic® jackets with mechanical ShearWrap™ load transfer, so no welding was done over the water, and SPiRe®+ panels rebuilt both caps in 2026 without replacing the dolphins.

  • PRODUCTS: PILEMEDIC® + SPIRE®+
  • APPLICATION: PILES & PILE CAPS
  • INDUSTRY: PORTS & MARINE
Steel pipe piles and pile cap reinforced with FRP at Port of Long Beach
2 cruise terminal dolphins repaired
mooring dolphins
2
steel pipe piles
8
pile diameter
36 in.
annular space in each jacket
4 in.

Project Details

LOCATION
Port of Long Beach, California
STRUCTURE
Two mooring dolphins, each on four 36-in. steel pipe piles with a concrete cap about 12 ft x 16 ft x 4 ft
QUAKEWRAP® SYSTEMS
PileMedic® jackets and ShearWrap™ connectors on the piles, SPiRe®+ panels on the caps
YEAR
2026
OWNER
Port of Long Beach
FACILITY OPERATOR
Carnival Cruise Line
ENGINEER OF RECORD
AtkinsRéalis
GENERAL CONTRACTOR
The Dutra Group

01 · THE CHALLENGE

Corroded Piles and Spalled Caps on a Busy Cruise Terminal

After decades in seawater, the two dolphins had extensive corrosion on the exposed steel piles, worst in the splash and tidal zones. In the caps, corroding reinforcing steel had cracked and spalled the concrete and left bars exposed, reducing the caps' structural integrity.

Replacing the dolphins would have been costly and disruptive at a busy port, and traditional repairs would have needed extensive scaffolding, conventional formwork and long schedules. The goal was to restore both structures with a faster method that kept interference with terminal operations to a minimum.

Mooring dolphin at the Port of Long Beach with heavily corroded steel pipe piles and a spalled concrete cap

02 · THE PILES

PileMedic® Jackets With ShearWrap™ Load Transfer

Spacers installed around each pile set a uniform 4-in. annular space between the corroded steel and the new jacket, and held supplemental reinforcing bars in the annulus. Where more load transfer was needed, ShearWrap™ connectors were installed. They transfer force mechanically, so no field welding or hot work was done over the water.

After the steel surface was prepared, a thin fiberglass PileMedic® laminate jacket was wrapped around each pile as a permanent stay-in-place form. The laminate arrives as a flexible sheet, so it was brought to the work area compactly and closed around the round pile. The annulus was filled with high-strength cementitious grout, with epoxy grout at the top and bottom to seal the repair, keep seawater off the cementitious grout and prevent washout during placement.

The jacket is more than a cover. The existing pile, supplemental bars, grout, load-transfer components and fiberglass shell together form a new structural section around each pile.

  • No welded shear tabs or field welding
  • Lightweight jackets installed without heavy lifting equipment
  • A new composite section around each original pile
Steel pipe pile under the dolphin cap fitted with bolted ShearWrap bands and vertical reinforcing bars anchored into the cap

03 · LOAD TRANSFER

Steel Pipe Pile Repair Without Field Welding

A grout jacket only works if force can pass between the old steel pile and the new reinforced grout. In conventional steel pile rehabilitation, shear tabs, headed studs or other connectors are welded to the pile for that purpose. Over water, that welding is hard to do well: access is restricted, the work area is wet, the corroded surface is poor, and every weld brings inspection and hot-work controls.

At Long Beach, ShearWrap™ components took the place of welded shear tabs. They engage the pile mechanically and carry load between the existing steel and the new reinforced-grout jacket. No welding equipment had to be set up at each pile, the work did not depend on finding weld-quality steel along the corroded length, and a major hot-work operation over the water was avoided.

  • Mechanical shear transfer instead of welded tabs or studs
  • No hot work over the water
  • Load path not dependent on the corroded steel surface
ShearWrap™ load-transfer bands on steel pipe piles below a Port of Long Beach dolphin cap with corroded reinforcing bars exposed

04 · THE CAPS

SPiRe®+ Panels as Form and Reinforcement

Each cap is about 12 ft x 16 ft in plan and 4 ft deep. Conventional repair would have meant building temporary forms beneath and around each cap and stripping them over the water afterward. Instead, deteriorated concrete was removed, the remaining bars were cleaned, and supplemental bars went in only where needed. SPiRe®+ pultruded fiberglass panels then enclosed the bottom and all four sides of each cap as permanent stay-in-place formwork.

The panels also add strength. Each provides reinforcement equivalent to about No. 6 Grade 60 bars at 3½ in. spacing, which significantly reduced the conventional steel the repair needed. High-strength cementitious grout bonded the original concrete, new steel and composite shell into a single structural element.

  • Stay-in-place formwork during grouting
  • Tensile reinforcement equal to about No. 6 bars at 3½ in.
  • A corrosion-resistant shell around the repaired cap
Dolphin cap with deteriorated concrete removed, exposing corroded reinforcing bars

CONSTRUCTION SEQUENCE

Piles First, Then the Caps

All eight piles were repaired and grouted before work moved up to the two dolphin caps.

GET A PILE REPAIR CONSULTATION
  1. Prepare

    Remove deteriorated concrete and clean corroded steel.

  2. Spacers and bars

    Install spacers and supplemental reinforcing bars on the steel piles.

  3. ShearWrap™

    Install ShearWrap™ load-transfer connectors where required.

  4. PileMedic® jackets

    Wrap PileMedic® laminate jackets around all eight piles.

  5. Grout the piles

    Place cementitious grout in the annular spaces.

  6. Epoxy seals

    Place epoxy grout seals at the upper and lower ends of each pile repair.

  7. Cap steel

    Add supplemental reinforcing steel in the dolphin caps where required.

  8. SPiRe®+ panels

    Assemble stay-in-place panels around the bottom and sides of each cap.

  9. Grout the caps

    Place cementitious grout inside the cap repair forms.

  10. Inspect

    Final inspection and completion of both dolphins.

05 · THE RESULT

Both Dolphins Restored Without Replacement

The rehabilitation restored two heavily deteriorated mooring dolphins without replacing them. The 36-in. steel pipe piles and the concrete caps were strengthened and now have a corrosion-resistant exterior.

Because the jackets and panels stay in place, no form stripping or extra finishing was needed. The light fiberglass materials were handled without large cranes or special lifting equipment on an active marine facility.

Each material did the job it suits best. The existing piles and serviceable cap concrete stayed in service, supplemental steel went in where it was needed, cementitious grout restored the section, epoxy grout sealed the pile ends, and the fiberglass jackets and panels supplied formwork, reinforcement and corrosion protection.

  • Stay-in-place composite forms on piles and caps
  • Less supplemental steel and congestion in the repair zone
  • Repaired members encapsulated in corrosion-resistant shells
Completed dolphin at the Port of Long Beach with jacketed piles and a cap enclosed in gray FRP panels
U.S. Navy divers repairing piles with PileMedic FRP

Have Piles That Need Repair?

Tell us about the piles and site conditions. Our team will recommend the right PileMedic® system and provide specifications for your engineer.