6840 S. Tucson Blvd, Tucson, AZ 85756, U.S.A.
GET A CONSULTATION

CASE STUDY

Port of Galveston Pier Beam Repair With Stay-in-Place FRP Shells

At a cargo pier in the Port of Galveston, 30 corroded beams that had lost up to 50% of their reinforcing steel, plus 6 piles, were repaired in the first application of the SPiRe® system as a custom-made stay-in-place form. This pier beam repair replaced temporary timber formwork with FRP shells that stay on as permanent protection.

  • PRODUCT: SPIRE®
  • APPLICATION: MARINE DECK
  • INDUSTRY: PORTS & MARINE
Port of Galveston pier with gray FRP shells installed along its corroded beams at the waterline
30 corroded beams repaired
corroded beams
30
loss of steel
50%
piles
6
project years
2024-25

Project Details

LOCATION
CHS terminal cargo pier, Port of Galveston, Texas
STRUCTURE
Concrete pier: marine deck, beams, girders and piles
SCOPE
30 corroded beams and 6 piles
QUAKEWRAP® SYSTEM
SPiRe® custom-molded sandwich FRP shells, made in two matching halves, as stay-in-place forms
SHELLS
3/8 in. thick, 2.2 lb per sq ft, rigid core with glass FRP skins, vinyl ester resin
ORIGINAL DESIGN
Conventional repair with timber and plywood formwork beneath the beams
FILL AND REINFORCEMENT
High-strength non-shrink grout with supplemental GFRP bars
CONTRACTOR
FRP Construction LLC ($1.8M contract, announced August 2022)
YEARS
2024-25

PROJECT VIDEO

Port of Galveston Deck and Pile Repair

Plays from YouTube

01 · THE CHALLENGE

Corroded Beams Under a Low, Confined Pier Deck

Years of salt-laden air and moisture had badly corroded the beams and deck of the concrete cargo pier at the CHS terminal in the Port of Galveston. Chlorides had corroded the reinforcing steel, cracking and spalling the concrete. Structural inspections found that up to 50% of the steel reinforcement had deteriorated in several elements, so the pier needed repair right away.

The owner's original design was a conventional repair: remove the deteriorated concrete, add reinforcement, build timber and plywood forms beneath each beam, place repair concrete and strip the forms. Beneath an operating terminal, every form had to be built over water in a confined space, held while the concrete cured, then taken apart, and by the time estimates were done the temporary formwork was one of the largest costs on the job. Gunite was not practical this close to the water either.

Underside of a Port of Galveston cargo pier with spalled concrete and corroded reinforcing steel in the beams

WHY THE DESIGN CHANGED

Pier Beam Repair Without Temporary Formwork

The conventional design was sound engineering. The difference was in how each repair had to be built beneath an active cargo terminal.

Conventional repair (original design) SPiRe® shell repair (as built)
Forms Timber and plywood built beneath each beam, over water Custom FRP shells made in a plant in two matching halves
During placement Forms supported while the repair concrete cures Shells anchored to the beam and sealed along the bottom seam
Fill Repair concrete High-strength non-shrink grout pumped through built-in ports
Added reinforcement Supplemental reinforcement Supplemental GFRP bars, with no new steel to corrode
After curing Forms dismantled and removed Nothing to remove: the shells stay on
Long-term surface Repaired concrete exposed to salt spray Permanent FRP skin against chloride intrusion

Have pier beams with the same problem?

Send us the beam sizes, clearance and condition. Our team will recommend the right QuakeWrap® system and provide specifications for your engineer.

GET A SEAWALL REPAIR CONSULTATION

02 · THE SHELLS

Split SPiRe® Shells Built for Tight Clearance

The approach came from the patented SPiRe® seawall system, where only one face of the wall can be reached: composite panels are anchored to that face, grout fills the gap, and the panel stays as permanent protection. At Galveston the idea was adapted to pier beams. Molds replicated the exact geometry of the deteriorated beams and girders, including the annular space to be grouted.

The first design called for one-piece shells, but the low clearance under the girders made them hard to maneuver into place. Each shell was instead made in two matching halves joined by an overlapping longitudinal seam along the bottom of the beam, which also absorbed the dimensional variations of an old structure. The shells were made in a plant from fiberglass composites and vinyl ester resin, with a rigid core between glass FRP skins, only 3/8 in. thick and 2.2 lb per sq ft. Grout ports and attachment details were built in before shipment.

  • Two-piece shells sized for low clearance
  • Grout ports and attachments built in at the plant
  • No timber formwork under the deck
Worker bonding spacers inside one half of a split SPiRe® FRP shell before installation at the Port of Galveston

03 · INSTALLATION

Installed and Grouted Under an Active Cargo Pier

Deteriorated concrete was removed and the beams were prepared. Spacers were bonded to the shells and supplemental nonmetallic GFRP bars were placed where needed to restore capacity. The light shell halves were moved under the deck with minimal equipment, lifted into place, aligned with the existing members, secured with all-thread anchor bolts into the host concrete and sealed along the longitudinal joint.

High-strength non-shrink grout was then pumped through the built-in ports into the cavity between shell and beam, bonding the parts into one composite member. Bolt ends were trimmed and capped with epoxy paste and a plastic cap. Once the grout cured, there was no formwork to strip.

  • Shells lifted and placed without heavy equipment
  • Nonmetallic GFRP bars inside the shell
  • Grouted through ports built into each shell
Worker pumping grout through a port into an FRP shell anchored to a pier beam at the Port of Galveston

INSTALLATION

How the Custom Shells Were Installed

GET A SEAWALL REPAIR CONSULTATION
  1. Make the shells

    Mold FRP shells to match the beams and girders, in two matching halves with grout ports built in.

  2. Prepare and fit out

    Remove deteriorated concrete, bond spacers to the shells and place GFRP bars where needed.

  3. Lift and anchor

    Lift the halves from below, anchor them with all-thread bolts and seal the bottom seam.

  4. Grout the annulus

    Pump non-shrink grout through the built-in ports to fill the space between shell and beam.

  5. Seal the bolts

    Trim bolt ends and encapsulate them in epoxy paste and a plastic cap.

04 · THE RESULT

Capacity Restored, Steel Sealed From Salt Spray

The completed repair restored the load-carrying capacity of the pier. The shells that served as forms are now permanent parts of the repaired beams, an impermeable skin against salt spray and chloride intrusion. In the design, the bond between the shells and the grout was assumed to be negligible, so the shells' structural contribution was conservatively not counted.

The procedure saved considerable time and cost during construction, because the effort went into permanent components rather than temporary works that would be thrown away. The bonded composite structure has a projected service life of more than 50 years with minimal maintenance. Prof. Ehsani's article on the project was the cover story of the September/October 2025 Concrete Repair Bulletin.

steel reinforcement lost
Up to 50%
shell thickness
3/8 in.
shell weight
2.2 lb/sq ft
projected service life
50+ yrs
Completed CHS cargo pier at the Port of Galveston with its beams encased in gray stay-in-place FRP shells
U.S. military crew training on SPiRe seawall repair

Have a Seawall or Deck That Needs Repair?

Tell us about the structure and site conditions. Our team will recommend the right QuakeWrap® system and provide specifications for your engineer.