6840 S. Tucson Blvd, Tucson, AZ 85756, U.S.A.
GET A CONSULTATION

NEWS

QuakeWrap® News

Project milestones, research grants, patents and awards for QuakeWrap® FRP products, newest first, with the original press releases and articles where they survive. The archive goes back to a 2004 QuakeWrap® e-bulletin.

U.S. Navy divers repairing piles with PileMedic FRP
2004 earliest e-bulletin in the archive

FEATURED STORY: JULY 2017

Arizona DOT's First CFRP Bridge Repair Restores 12 Collision-Damaged Girders

Trucks had hit the precast prestressed girders of two I-17 bridges in downtown Phoenix many times. One edge girder at the Jefferson Street underpass had severed strands and was assumed to have lost 50% of its flexural strength. Eleven girders at the 19th Avenue overpass had lighter damage, assumed at 20%. With about 100,000 vehicles a day on I-17 (2010 count), replacing girders was not an option.

For its first carbon FRP project, ADOT's Bridge Group wrote a performance-based specification, adapted from Caltrans, and put the work out to open bid. FNF Construction won the contract, FRP Construction LLC installed the system, and QuakeWrap Inc. supplied the QuakeWrap® carbon fabric and epoxy and, under that subcontract, the strengthening design to the AASHTO guide specification ADOT required.

Crews worked nights from 9 p.m. to 5 a.m., starting April 24, 2017. Longitudinal TU27C carbon fabric went on the bottom and lower sides of the girders, with 6 in. U-wrap strips at 12 in. on center to hold any spalled concrete. The 19th Avenue bridge was done in about 15 days against a 20-day schedule, and Jefferson Street over a single weekend in May 2017. According to ADOT, the 19th Avenue overpass is no longer listed as structurally deficient.

Girders repaired
12
Assumed strength loss
20% to 50%
19th Ave. installation
About 15 days
Work window
9 p.m. to 5 a.m.
Crews on lifts installing carbon FRP strips on the girders of the I-17 19th Avenue bridge in Phoenix during night work

PROJECT DETAILS

I-17 Jefferson Street and 19th Avenue Bridges

AGENCY
Arizona Department of Transportation (ADOT) Bridge Group
LOCATION
I-17 at Jefferson Street (underpass) and 19th Avenue (overpass), Phoenix, Arizona
STRUCTURES
Precast prestressed AASHTO Type II girder bridges built in 1959 and 1961
DAMAGE
Repeated truck collisions: spalls, exposed and severed prestressing strands
REPAIRED
1 girder at Jefferson Street, 11 girders at 19th Avenue, over 40 to 50 ft lengths
STRENGTH ADDED
1,027 k-ft vs 1,000 k-ft required (Jefferson); 392 k-ft vs 360 k-ft (19th Ave.)
SYSTEM
Externally bonded QuakeWrap® TU27C unidirectional carbon fabric, plus 6 in. U-wrap strips
DESIGN BASIS
AASHTO Guide Specifications for Design of Bonded FRP Systems (1st ed., 2012)
QUALITY CONTROL
Unopened packaging, fabric lot and resin batch numbers logged per girder, daily ASTM D3039 witness panels by Western Technologies
TEAM
FNF Construction (general contractor), FRP Construction LLC (installer), QuakeWrap Inc. (materials)
PUBLISHED
IBC 18-10, 35th International Bridge Conference, by Mo Ehsani, Tadd Johnson and William Downes (ADOT)

Our ADOT Bridge Group focuses on using new and innovative bridge-repair technologies that enhance safety while saving time and taxpayer dollars.

William DownesSenior Bridge Engineer, ADOT, to Composites Manufacturing magazine (2017)
Bridges
2
Girders
12
Fabric per night
About 500 sq ft
Traffic on I-17 (2010)
100,000 vehicles a day

FEATURED STORY: USDOT SBIR

A Federal Research Grant for No-Dig Repair of Oil and Gas Pipelines

Most oil and gas transmission pipes are repaired from the outside, which means digging up the line at every damaged spot. In June 2020 the U.S. Department of Transportation's Small Business Innovation Research (SBIR) program awarded QuakeWrap a Phase I contract to repair these pipes from the inside instead, under the topic 'Internal Repair of Steel Transmission Pipelines (20-PH2)'.

The work is funded by the Pipeline and Hazardous Materials Safety Administration (PHMSA). Phase I, worth $150,000 in fiscal 2020, aimed at proof of concept: QuakeWrap's lab tested the repair for high pressure and chemical resistance and developed a design method. QuakeWrap then won the Phase II award, listed in USDOT's fiscal 2021 awards: $1,000,000 to develop the repair method, per QuakeWrap's March 15, 2022 press release.

The repair uses SuperLaminate™, carbon fabric saturated with epoxy and wrapped around a packer. A tethered automated guide vehicle carries the packer from an existing tool launcher to the damaged spot, the packer inflates against the pipe wall and heat cures the laminate, leaving a sleeve inside the pipe like a stent. USDOT's Volpe Center featured the project as an SBIR success story in 2025, noting a current reach of 500 ft from the launch site.

  • Agency: U.S. DOT SBIR program, funded by PHMSA
  • Project: No-Dig Point Repair Technology for Steel O&G Pipelines
  • Phase I: $150,000, fiscal 2020; Phase II: fiscal 2021 award list
  • Launched from existing access sites used for pipe cleaning and inspection
Frame from a 2010 QuakeWrap demonstration of SuperLaminate bridging a gap in a steel pipe
TYPE
PRODUCT

News Archive

Showing 51 stories

STAY INFORMED

Get QuakeWrap® News by Email

Subscribe to hear about new podcast episodes, case studies and speaking events.

SUBSCRIBE
  • Product news

    The latest on QuakeWrap® FRP products for infrastructure repair.

  • Case studies

    New case studies as projects are completed.

  • Podcast and speaking events

    Upcoming podcast episodes and conference talks.

Have a structure to repair now?

Skip the newsletter and talk to our team about your project.

GET A CONSULTATION
Work platform inside the 12-ft Minneapolis storm tunnel with StifPipe carbon layers applied around the tunnel wall

Working on a Repair Like These?

Tell us about the structure. Our team will recommend the right QuakeWrap® system and provide specifications for your engineer.