40 ASR-Damaged Bridge Piles Encased Underwater in a Crocodile River

Under the Captain Cook Highway bridge over the Barron River estuary near Cairns, Queensland, all 40 prestressed piles in the four river piers were encased with seamless PileMedic® jackets and underwater grout. Divers worked inside steel cages, and the job took about five working weeks.

  • PRODUCT: PILEMEDIC®
  • APPLICATION: BRIDGE PILES
  • INDUSTRY: TRANSPORTATION
Workers in orange high-visibility shirts spreading epoxy on a long sheet of white laminate on a table under a bridge
40 prestressed concrete piles encased underwater
piles in four river piers
40
working days on site
~35
confinement vs. 300 psi required
648 psi
minimum clear pile spacing
12 in.

Project Details

OWNER
Queensland Department of Transport and Main Roads (DTMR)
LOCATION
Captain Cook Highway southbound bridge over the Barron River estuary, about 4.5 miles (7 km) north of Cairns, Queensland, Australia
STRUCTURE
1977 bridge, 579 ft (176 m) long, seven 77 ft (23 m) spans; blade piers on pile caps, each on 10 octagonal prestressed concrete piles
DAMAGE
Alkali-silica reaction (ASR) cracking
QUAKEWRAP® SYSTEM
Two-ply PileMedic® laminate jackets, 25 in. diameter, filled with cementitious underwater grout
GENERAL CONTRACTOR
Roadtek (DTMR)
UNDERWATER CONTRACTOR
JD Marine
QUAKEWRAP® ROLE
QuakeWrap (Australia) provided training and technical advice to the divers
COMPLETED
2015

PROJECT VIDEO

Repair of ASR-Contaminated Piles in a Crocodile-Infested River

Plays from YouTube

01 · THE CHALLENGE

Fifteen Years Looking for a Repair That Fit

In 2000, severe cracking was found in 13 of the 40 piles in the four river piers, and analysis traced it to ASR. DTMR chose encasement as the long-term treatment and set two criteria: at least 300 psi (2.1 MPa) of confinement to slow ASR, and a barrier against chlorides, moisture and oxygen.

The site ruled out the usual answers. Piles stand as close as 12 in. apart, too tight for individual concrete jackets, and the work had to be done underwater in a murky estuary with crocodiles, bull sharks and jellyfish. Concrete encasement estimates exceeded the funding, a 2003 FRP prototype could not hold fresh grout pressure, and seamed half-shell jackets were judged unsuitable. By 2014, 22 piles were cracked.

Concrete bridge blade pier on a wide pile cap at the water line, with the tops of piles visible just above the water

02 · THE SOLUTION

Seamless Jackets Built Around Each Pile, Underwater

In 2014, PileMedic® was identified as meeting DTMR's technical needs at around 40% of the previously tendered prices for concrete encasement, and it was approved as a trial installation. Roadtek undertook the work, with QuakeWrap (Australia) training the commercial divers and providing technical advice.

Each jacket was two plies of laminate around a 2 in. grout annulus, for a 25 in. diameter. The published design check gives about 648 psi (4.5 MPa) of confinement, more than double DTMR's 300 psi criterion.

  • Steel cage around each pier to protect the diving crew
  • 4 ft wide laminate cut to 165 in. and coated with epoxy paste on the barge
  • Divers wrapped it over spacers and held it with ratchet straps while the epoxy cured underwater
  • First jacket set about 18 in. below the mud line, each next one lapped 4 in.
  • Annulus filled with cementitious underwater grout by tremie
Workers in orange shirts and hats lifting a curved white sheet of laminate over a steel mesh cage beside a concrete pier

03 · THE RESULT

All 40 Piles in About Five Working Weeks

The crew finished in around 35 working days in 2015. A typical pier took 1 day to install the protective cage, 4 days to wrap its 10 piles and place the grout, and 1 day to move to the next pier.

The final cost was A$0.95 million. The 2008 bid for concrete encasement was A$2.0 million, about A$2.46 million in 2015 dollars. Our Learn article on this bridge covers the full cost comparison, the 15-year timeline and the worked confinement check.

piles encased
40
piers
4
working days
~35
final cost
A$0.95M
White cylindrical FRP jackets on piles beneath a concrete pile cap, behind a wire mesh cage, with a barge and worker in the background
U.S. Navy divers repairing piles with PileMedic FRP