CASE STUDY
40 ASR-Damaged Bridge Piles Encased Underwater in a Crocodile River
Under the Captain Cook Highway bridge over the Barron River estuary near Cairns, Queensland, all 40 prestressed piles in the four river piers were encased with seamless PileMedic® jackets and underwater grout. Divers worked inside steel cages, and the job took about five working weeks.

Project Details
- OWNER
- Queensland Department of Transport and Main Roads (DTMR)
- LOCATION
- Captain Cook Highway southbound bridge over the Barron River estuary, about 4.5 miles (7 km) north of Cairns, Queensland, Australia
- STRUCTURE
- 1977 bridge, 579 ft (176 m) long, seven 77 ft (23 m) spans; blade piers on pile caps, each on 10 octagonal prestressed concrete piles
- DAMAGE
- Alkali-silica reaction (ASR) cracking
- QUAKEWRAP® SYSTEM
- Two-ply PileMedic® laminate jackets, 25 in. diameter, filled with cementitious underwater grout
- GENERAL CONTRACTOR
- Roadtek (DTMR)
- UNDERWATER CONTRACTOR
- JD Marine
- QUAKEWRAP® ROLE
- QuakeWrap (Australia) provided training and technical advice to the divers
- COMPLETED
- 2015
PROJECT VIDEO
Repair of ASR-Contaminated Piles in a Crocodile-Infested River
Plays from YouTube
01 · THE CHALLENGE
Fifteen Years Looking for a Repair That Fit
In 2000, severe cracking was found in 13 of the 40 piles in the four river piers, and analysis traced it to ASR. DTMR chose encasement as the long-term treatment and set two criteria: at least 300 psi (2.1 MPa) of confinement to slow ASR, and a barrier against chlorides, moisture and oxygen.
The site ruled out the usual answers. Piles stand as close as 12 in. apart, too tight for individual concrete jackets, and the work had to be done underwater in a murky estuary with crocodiles, bull sharks and jellyfish. Concrete encasement estimates exceeded the funding, a 2003 FRP prototype could not hold fresh grout pressure, and seamed half-shell jackets were judged unsuitable. By 2014, 22 piles were cracked.

02 · THE SOLUTION
Seamless Jackets Built Around Each Pile, Underwater
In 2014, PileMedic® was identified as meeting DTMR's technical needs at around 40% of the previously tendered prices for concrete encasement, and it was approved as a trial installation. Roadtek undertook the work, with QuakeWrap (Australia) training the commercial divers and providing technical advice.
Each jacket was two plies of laminate around a 2 in. grout annulus, for a 25 in. diameter. The published design check gives about 648 psi (4.5 MPa) of confinement, more than double DTMR's 300 psi criterion.
- Steel cage around each pier to protect the diving crew
- 4 ft wide laminate cut to 165 in. and coated with epoxy paste on the barge
- Divers wrapped it over spacers and held it with ratchet straps while the epoxy cured underwater
- First jacket set about 18 in. below the mud line, each next one lapped 4 in.
- Annulus filled with cementitious underwater grout by tremie

03 · THE RESULT
All 40 Piles in About Five Working Weeks
The crew finished in around 35 working days in 2015. A typical pier took 1 day to install the protective cage, 4 days to wrap its 10 piles and place the grout, and 1 day to move to the next pier.
The final cost was A$0.95 million. The 2008 bid for concrete encasement was A$2.0 million, about A$2.46 million in 2015 dollars. Our Learn article on this bridge covers the full cost comparison, the 15-year timeline and the worked confinement check.
- piles encased
- 40
- piers
- 4
- working days
- ~35
- final cost
- A$0.95M

Products & Applications Used
-

PileMedic®
Pile repair and strengthening, including underwater.
Explore PileMedic® -

PileMedic® Pile Jackets
Seamless laminate jackets built on the pile, in the dry or underwater.
Explore Pile Jackets -

Bridge Piling
Concrete, steel and timber bridge piles repaired in place.
Explore Bridge Piling -

Pile Repair
Timber, steel and concrete piles, without cofferdams.
Explore Pile Repair
MORE PROJECTS
Related Projects
-

Missouri DOT I-70/I-270, St. Louis
49 corroded steel H-piles under four interstate bridges restored in two weeks.
View case study -

Port of Seattle Terminal 18
Prestressed piles with DEF retrofitted with no shutdown of port service.
View case study -

Agricultural Port, Chesapeake, Virginia
500+ timber piles restored with PileMedic® while the dock stayed open.
View case study
Read More About This Project
Have Bridge Piles That Need Repair?
Tell us about the bridge, the piles and the site. Our team will recommend the right PileMedic® system and provide specifications for your engineer.