6840 S. Tucson Blvd, Tucson, AZ 85756, U.S.A.
GET A CONSULTATION

CASE STUDY

North Dakota DOT Study of FRP Culvert Joint Repair

The North Dakota Department of Transportation tested several repair strategies on a reinforced concrete pipe culvert. Its report found the joints lined with QuakeWrap® carbon and glass FRP remained sealed two years later.

  • PRODUCT: WET LAYUP CFRP & GFRP
  • APPLICATION: CULVERT
  • OWNER: STATE DOT
Green glass fabric lining a joint inside the reinforced concrete pipe culvert in the NDDOT study
installation
2009
follow-up inspection
2011
carbon and glass, two joints each
2 fabrics
QuakeWrap materials and onsite supervision
$18,910

Project Details

REPORT
Reinforced Concrete Pipe Repair, Experimental Study ND 09-01, Final Report (March 2012)
AGENCY
North Dakota Department of Transportation, Materials & Research Division
STRUCTURE
Twin 88 in. x 54 in. reinforced concrete arch pipe culverts
LOCATION
Interstate 29 northbound near Reference Point 75, north of Fargo, Cass County, North Dakota
QUAKEWRAP® SYSTEM
Wet layup: QuakeWrap TB20C carbon fabric and VB26G glass fabric, QuakeBond™ J300SR resin, J201TC tack coat
INSTALLER
Subsurface, Inc., supervised by a QuakeWrap representative
QUAKEWRAP SCOPE
All materials, onsite supervision and training

01 · THE STUDY

Comparing Repair Strategies on a Real Culvert

NDDOT's Materials & Research Division documented several contractors' repair methods on the same reinforced concrete pipe culvert. Subsurface, Inc. sealed the joints with oakum rope and water-activated flexible foam, then installed QuakeWrap's repair under the supervision of a QuakeWrap representative.

Rain and cold weather were factors. A significant moisture event delayed the installation for nearly four days, and the pipe was kept heated and above freezing so the system could cure.

Two workers saturating QuakeWrap fabric with resin on a table in a job trailer before installation in the culvert

02 · THE INSTALLATION

Two Fabrics, Two Layers Per Joint

QuakeWrap used the wet layup method. Fabric was saturated with QuakeBond™ J300SR resin in an onsite trailer, carried into the pipe on a PVC pipe, and placed over a QuakeBond™ J201TC tack coat applied to the sides and top of the pipe. Workers smoothed out wrinkles with squeegees.

Two fabrics were tried on two joints each: QuakeWrap TB20C carbon fabric and VB26G glass fabric. Each joint received two layers, followed by a 24-hour cure.

  1. FRP fabric (TB20C carbon or VB26G glass)2 layers
  2. QuakeBond™ J201TC tack coatSides and top
  3. Concrete pipe jointHost

03 · THE RESULT

Still Bonded and Sealed in 2011

In its 2011 follow-up, the report states that the QuakeWrap carbon fiber and fiberglass "bonded to the concrete very well and those joints remained sealed and didn't show any signs of movement."

When the twin arch pipes were excavated and removed on June 13, 2011, the sections repaired with QuakeWrap lifted out of the trench together. The report notes the backhoe operator could not separate them without breaking the concrete.

The cost of QuakeWrap materials and onsite supervision was $18,910.

installed
2009
joints still sealed
2011
QuakeWrap carbon fiber lining over a joint inside a concrete culvert in the North Dakota DOT study, October 2009

Have a Culvert That Needs Repair?

Tell us about the culvert, its size and condition. Our team will recommend the right QuakeWrap® system and provide specifications for your engineer.