6840 S. Tucson Blvd, Tucson, AZ 85756, U.S.A.
GET A CONSULTATION

CASE STUDY

I-35 Storm Tunnel Rehabilitation, Minneapolis

A fully structural StifPipe® liner, built up layer by layer by wet layup, renewed a 20-ft section of a 12-ft concrete-lined storm tunnel for the Minnesota Department of Transportation, far below the city and a long way from the nearest manhole.

  • PRODUCT: STIFPIPE®
  • APPLICATION: STORM TUNNEL
  • INDUSTRY: TRANSPORTATION & STORMWATER
Two installers in white suits applying StifPipe layers by wet layup to the crown of the 12-ft I-35 storm tunnel in Minneapolis
12 ft storm tunnel lined with StifPipe®
tunnel diameter
12 ft
fully structural section
20 ft
StifPipe® layers
8
installation
3 weeks

Project Details

OWNER
Minnesota Department of Transportation (MnDOT)
LOCATION
Minneapolis, Minnesota
STRUCTURE
12-ft concrete-lined storm tunnel, I-35W/I-94 tunnel system
PROJECT ENGINEER
Brierley Associates
GENERAL CONTRACTOR
PCI Roads
FRP INSTALLER
FRP Construction
QUAKEWRAP® SYSTEM
StifPipe®, installed internally by wet layup
QUAKEWRAP® ROLE
StifPipe® materials and design support for the project engineer
COMPLETED
March 2019

PROJECT VIDEO

Storm Tunnel Rehab and Repair in Minneapolis

Plays from YouTube

01 · THE CHALLENGE

A Distressed Liner Deep Under the City

The I-35W/I-94 storm tunnel system under Minneapolis ranges from 8 to 14 ft in diameter and runs 50 to 130 ft underground. During storms the tunnel surcharges, and cycles of pressurization and depressurization had distressed the concrete liner and eroded the friable St. Peter sandstone around it, leaving voids behind the liner.

A grouting and crack sealing program restored most of the system. One 20-ft segment of the 12-ft tunnel, more than 100 ft below grade, still had high groundwater pressure, inflow and a noticeable loss of effective liner thickness. Brierley Associates, the project engineer, concluded that this segment needed a fully structural liner designed for the full soil and hydrostatic load.

Access was the other problem. The closest manhole was about 3,200 ft from the repair, and groundwater and snow melt were running through the tunnel. Before lining, PCI Roads and Brierley stopped the active leaks with dewatering and polyurethane grout injection and added pressure relief ports in the tunnel wall.

Crew in rain gear on a platform in the I-35 storm tunnel while a groundwater relief port is installed in the wall

02 · THE SOLUTION

StifPipe® Built in Place, Layer by Layer

A carbon-only FRP liner would have needed an excessive number of carbon layers to carry the external load. The project engineer selected StifPipe®, whose proprietary 3D core fabric adds stiffness without stacking more carbon. The fabrics and resins reached the repair point in boxes and drums, by skid steer more than half a mile through the tunnel.

The liner was designed for 100 psi of external hydrostatic pressure and was first tried in mock installations at the QuakeWrap R&D lab. FRP Construction then installed it by wet layup.

  • Primer on the prepared concrete, then 4 carbon fiber, 2 glass fiber and 2 core fabric layers
  • Three FRP layers tucked into grooves cut in the concrete liner and sealed with thickened epoxy at the ends, so no water can get behind the liner
  • Repair area sealed off with plastic sheets for humidity and temperature control
  • Groundwater and snow melt carried past the work through bypass pipes
  • Heaters raised the air from 63°F to 75°F to speed the cure
  • Moisture, temperature and pull-off tests recorded throughout, with Brierley Associates inspectors on site
View along the work platform inside the 12-ft Minneapolis storm tunnel during the StifPipe installation, with materials staged at the far end

03 · THE RESULT

Finished Ahead of the Spring Melt

The crew had to finish before snow above ground melted and sharply raised the flows and pumping costs. With the heaters running, saturated layers were dry to the touch within a couple of hours, and the StifPipe® installation was complete in three weeks, ahead of the spring rain and snow melt, with no significant issues at the site.

The project set the record at the time for the deepest application of an FRP system for fully structural pipe or tunnel rehabilitation.

installation
3 weeks
completed
March 2019
Work platform inside the 12-ft Minneapolis storm tunnel with StifPipe carbon layers applied around the tunnel wall
Culvert repaired with StifPipe

Have a Pipe or Tunnel That Needs Repair?

Tell us about the pipe or tunnel, its loads and access. Our team will recommend the right QuakeWrap® system and provide specifications for your engineer.